Introduction

Welcome to the May newsletter for 13-19 The Green, Southall, which will keep you updated on the progress of this development. This new 23 storey building will provide 424-bed student accommodation with associated public realm improvements for the wider public to enjoy. 

The plans were approved by Ealing Council in July 2025, and work on site began in October 2025.

Development News

The concrete structure for the stairs and lifts is being constructed. The basement and ground floor concrete slabs have been poured, and we will be progressing our concrete slabs up to level 3. The tower crane on site will be extended twice over the next 7 weeks increasing the height of the tower crane.

The works are expected to complete on time for students to move into their new accommodation in August 2027.


Timeline

Autumn 2025 – Building works commence on site
August 2027– Building works complete, and students move in

Get in Touch with Us

Please contact us by emailing team@thegreensouthall.co.uk or call the team on 0800 8611 218 with any questions about the development.

If you would like this newsletter in an alternative language, please visit our website www.southallthegreen.co.uk.

Latest

Notice of Road Closure

We would like to bring to your attention that we have arranged for a partial road closure for tower crane activities on The Green.  Once the closure is in place, it will not be able to be removed until the works are completed.  Traffic management will be in place with a signed diversion. Pedestrian access […]

Read more

July 2026

Introduction Welcome to the July newsletter for 13-19 The Green, Southall, which will keep you updated on the progress of this development. This new 23 storey building will provide 424-bed student accommodation with associated public realm improvements for the wider public to enjoy. Background The planning application for the scheme was approved in 2025 with […]

Read more

May 2026

Introduction Welcome to the May newsletter for 13-19 The Green, Southall, which will keep you updated on the progress of this development. This new 23 storey building will provide 424-bed student accommodation with associated public realm improvements for the wider public to enjoy.  The plans were approved by Ealing Council in July 2025, and work […]

Read more

February 2026

Introduction Welcome to the February newsletter for 13-19 The Green, Southall, which will keep you updated on the progress of this development. This new 23 storey building will provide 424-bed student accommodation with associated public realm improvements for the wider public to enjoy. Tide Construction is pleased to say construction work commenced in October 2025. […]

Read more

October 2025

Introduction Welcome to the first newsletter for 13-19 The Green, Southall, which will keep you updated on the progress of this development. This new 23 storey building will provide 424-bed student accommodation with associated public realm improvements for the wider public to enjoy. Tide Construction is pleased to say construction work is starting in October […]

Read more

Contact us

For further information or to ask us any questions, please reach out via
FREEPOST - CRATUS COMMUNICATIONS